Itens da Licitação
| Material |
Unid. |
Qtde. |
Preço Unit. |
Preço Total |
| Total do Fornecedor: |
0,00 |
Fornecedor: CB SERVIÇOS DE TECNOLOGIA DA INFORMACAO LTDA, CPF/CNPJ 52.783.531/0001-00
|
| IMPLANTAÇAO DE INFRAESTRUTURA REDE COMPLETA – CENTRO CULTURAL – ERACI GUILARDI VIDAL |
UN |
1,00 |
13.314,94000 |
13.314,94 |
| RACK 6U |
UN |
1,00 |
726,40000 |
726,40 |
| MIKROTIK ROUTERBOARD RB 750 GR3 HEX 880 MH 256 MB GIGA |
UN |
1,00 |
776,00000 |
776,00 |
| SWITCH 8P GIGA |
UN |
1,00 |
232,00000 |
232,00 |
| UNIFI INDOR GIGA WIFI 7 SHD |
UN |
3,00 |
2.877,76000 |
8.633,28 |
| ORGANIZADOR 1U |
UN |
1,00 |
49,60000 |
49,60 |
| MODULOS COM CONECTORES RJ 45 FEMEA |
UN |
3,00 |
18,01800 |
54,05 |
| CONDULETE 4 X 2 BRANCO PARA 3 POSTOS |
UN |
3,00 |
12,86400 |
38,59 |
| MODULOS CEGOS |
UN |
6,00 |
5,76000 |
34,56 |
| CONECTORES PARA CONDULETE |
UN |
3,00 |
1,95400 |
5,86 |
| CONECTOR RJ 45 FEMEA |
UN |
3,00 |
18,01400 |
54,04 |
| CONECTOR RJ 45 MACHO |
UN |
3,00 |
2,24000 |
6,72 |
| CABO DE REDE CAT 5 BRANCO |
M |
350,00 |
3,48800 |
1.220,80 |
| REGUA DE TOMADA COM 4 TOMADAS |
UN |
1,00 |
33,04000 |
33,04 |
| MAO DE OBRA PARA MONTAGEM DO RACK, EQUIPAMENTOS, PASSAGEM DE CABEAMENTO, INSTALAÇAO DOS UNIFI. |
UN |
1,00 |
1.450,00000 |
1.450,00 |
| IMPLANTAÇAO DE INFRAESTRUTURA REDE COMPLETA – ESCOLA MENINO DEUS |
UN |
1,00 |
10.900,30000 |
10.900,30 |
| CABO DE REDE CAT 5E |
M |
50,00 |
3,48800 |
174,40 |
| CABO DROP 1 VIA |
M |
80,00 |
1,28000 |
102,40 |
| CABO DE REDE CAT 5E CAPA DUPLA |
M |
210,00 |
4,72000 |
991,20 |
| ROTEADOR 4 ANTENAS |
UN |
7,00 |
356,68900 |
2.496,82 |
| SWITCH GIGA 24 P |
UN |
1,00 |
1.104,00000 |
1.104,00 |
| SWITCH GIGA 8 P |
UN |
1,00 |
232,00000 |
232,00 |
| CONVERSOR DE MIDIA GIGA LADO A |
UN |
1,00 |
395,20000 |
395,20 |
| CONVERSOR DE MIDIA GIGA LADO B |
UN |
1,00 |
395,20000 |
395,20 |
| CONECTOR VERDE APC PARA CONVERSOR DE MIDIA |
UN |
2,00 |
7,82000 |
15,64 |
| UNIFI INDOOR GIGA WIFI 7 |
UN |
1,00 |
2.877,76000 |
2.877,76 |
| CONECTOR RJ 45 MACHO |
UN |
7,00 |
2,24000 |
15,68 |
| MOBILIZAÇAO DE EQUIPE E MAO DE OBRA PARA EXECUÇAO DA INFRAESTRUTURA DE REDE. |
UN |
1,00 |
2.100,00000 |
2.100,00 |
| IMPLANTAÇAO DE INFRAESTRUTURA REDE COMPLETA – GINASIO POLIESPORTIVO NASCENTE DO PROGRESSO |
UN |
1,00 |
5.425,21000 |
5.425,21 |
| RACK 6 U |
UN |
1,00 |
726,41000 |
726,41 |
| ELETRODUTO ¾ PVC CINZA |
UN |
5,00 |
18,33690 |
91,68 |
| ABRAÇADEIRAS ¾ PVC CINZA TIPO “D” |
UN |
15,00 |
1,42400 |
21,36 |
| CONDULETE ¾ PVC CINZA TIPO ‘D” |
UN |
3,00 |
10,97500 |
32,93 |
| ADAPTADORES (CONECTORES) PARA CONDULETE ¾” |
UN |
4,00 |
2,01500 |
8,06 |
| CABO DE REDE CAT 6 BLINDADO |
M |
125,00 |
12,80000 |
1.600,00 |
| CONECTOR RJ 45 FEMEA COM MODULO |
UN |
3,00 |
18,01800 |
54,05 |
| CONECTOR RJ 45 MACHO |
UN |
10,00 |
2,24000 |
22,40 |
| MODULO CEGO |
UN |
6,00 |
5,76000 |
34,56 |
| NOBREAK 1200 VA |
UN |
1,00 |
1.583,76000 |
1.583,76 |
| MOBILIZAÇAO DE EQUIPE E MAO DE OBRA PARA EXECUÇAO DA INFRAESTRUTURA DE REDE. |
UN |
1,00 |
1.250,00000 |
1.250,00 |
| Total do Fornecedor: |
29.640,45 |
| Total: |
29.640,45
|